Advancing Efficient Energy Conversion Through SNG Technology
The main installation of the cryogenic cold box unit for a coke oven gas-to-hydrogen and SNG (Synthetic Natural Gas) project has been successfully completed, marking a significant milestone in the development of advanced gas conversion technology.The project focuses on the high-value utilization of coke oven gas by converting industrial by-product gases into clean energy products, including hydrogen and synthetic natural gas.
Through advanced gas treatment and separation technologies, the project enables efficient recovery of valuable components from coke oven gas, helping industries improve resource utilization efficiency while reducing energy waste.As global industries continue to pursue cleaner and more sustainable energy solutions, SNG projects based on industrial gas resources are becoming an important approach to maximizing existing resources and improving energy efficiency.

Coke Oven Gas Utilization: Turning Industrial Waste Gas into Valuable Energy
This project adopts an integrated process route, including: Gas desulfurization, gas storage and compression, fine purification treatment, gas conversion, carbon dioxide removal, drying and membrane separation, compression and product delivery.
After completion, the facility will achieve an annual production capacity of approximately: 140 million cubic meters of synthetic natural gas, 80,000 tons of synthetic ammonia.The project demonstrates how advanced **SNG technology** can transform industrial by-product gases into reliable energy resources.

Cryogenic Cold Box Unit: A Core Component of Gas Separation System
Overcoming Complex Installation Challenges
The installation of large-scale cryogenic equipment involves significant technical challenges. The project team implemented specialized solutions to ensure smooth execution.
High Precision Installation Requirements
Cryogenic equipment requires extremely accurate installation because even minor deviations can affect long-term operation. To ensure installation quality, the engineering team applied: advanced alignment measurement tools, precision positioning methods, strict welding inspection procedures. These measures ensured that every installation step met the required technical standards.
Limited Construction Space and Heavy Equipment Handling
Due to restricted onsite conditions, transporting and lifting large equipment required careful planning. Before installation, detailed lifting simulations and safety evaluations were conducted to: select suitable lifting equipment, optimize installation procedures, reduce operational risks.This preparation helped achieve successful equipment positioning during the installation process.
Managing Multiple Construction Activities
Large industrial projects often involve simultaneous activities, including: civil construction, equipment installation, pipeline installation, electrical and instrumentation work. To maintain project progress, the team adopted an efficient management approach with: detailed construction schedules, clear responsibility allocation, coordinated communication between different teams. This ensured that multiple work packages progressed safely and efficiently.